Spring 2026 Update: Beaver River Bridge Replacement Project
The Beaver River Bridge project is currently in stage four of construction. The mainline Pennsylvania Turnpike lanes have been shifted south to allow for earthwork, grading and asphalt paving to realign the roadway with the new river crossing structures. All four piers and pier tables for the westbound Beaver River Bridge crossing have been completed. Fifteen-foot segmental concrete placements have been completed from westbound piers 1 and 4 headings. Form travelers have been moved to westbound piers 2 and 3 for segmental construction at those headings, which is in progress. Segmental construction at these headings will continue into fall 2026,…